Rows of empty blue and orange industrial warehouse racking in a large facility.

Walmart DC 7520 – Racking Expansion

Plainfield, INIndustrial In progress

A racking expansion inside an active Walmart distribution center in Plainfield, Indiana, with electrical and fire protection coordination.

Expanding storage inside a live distribution center.

Adding racking to a distribution center that's already running means every electrical and fire protection tie-in has to be planned around the facility's schedule, not the contractor's. At Walmart DC 7520, we delivered the expansion on an accelerated timeline, with shutdowns planned in advance and kept short.

Project Specifications

Building Systems
Racking expansion; electrical and fire protection coordination
Site Conditions
Shutdown planning and an accelerated schedule inside an operating facility