Gray industrial building with orange cones, exposed beams, AC units, and red safety flags on the roof.

Hankook Tire – Engineering Building

Clarksville, TNIndustrial Completed 2021

A design-build second-story engineering addition constructed on top of and inside Hankook Tire's operating Clarksville plant.

A second story built over a working floor.

Hankook needed engineering office space and more room for tire product storage, and the only place to put both was on and inside a plant that couldn't pause. We delivered the project design-build: a second-story Engineering Building addition, conversion of first-floor office space to product storage, secondary stair access, and a new siphonic drain system.

Structural work happened over occupied space with production continuing below. The new space opened in 2021 without interrupting plant operations.

Project Specifications

Building Systems
Second-story addition; secondary stair access; new siphonic drain system
Site Conditions
Structural work over occupied space with production continuing below